Court delays block Keystone XL pipeline construction in 2019

Avatar photo

Published

on

Trump signing the Presidential memoranda to advance the construction of the Keystone XL and Dakota Access pipelines on Jan. 24, 2017. PHOTO COURTESY OF WIKIPEDIA

ASSOCIATED PRESS

BILLINGS (AP) — An executive for the company proposing the Keystone XL oil pipeline from Canada’s oil sands into the U.S. says it has missed the 2019 construction season due to court delays.

TransCanada executive vice president Paul Miller made the statement during a May 3 earnings call with analysts. The company also announced it was changing its name to TC Energy Corp.

Plans to begin construction of the long-delayed pipeline got blocked last November when a federal judge in Montana ordered additional environmental reviews of the project.

President Donald Trump has been trying to push it through. He issued a new permit for Keystone last month.

The $8 billion line would carry up to 830,000 barrels (35 million gallons) of crude daily, along a route stretching from Canada to Nebraska.

Upcoming Events

september, 2024

Filter Events

08jul(jul 8)6:00 pm16sep(sep 16)6:00 pmBike Big Sky(july 8) 6:00 pm - (september 16) 6:00 pm Event Type :SportsEvent City:Big Sky

15jul(jul 15)9:00 am16sep(sep 16)12:00 pmHike Big Sky(july 15) 9:00 am - (september 16) 12:00 pm Event Type :OtherEvent City:Big Sky

15jul(jul 15)6:00 pm23sep(sep 23)6:00 pmBike Big Sky(july 15) 6:00 pm - (september 23) 6:00 pm Event Type :SportsEvent City:Big Sky

17jul(jul 17)12:00 pm16sep(sep 16)1:00 pmCommunity Yoga Every Wednesday @ Noon(july 17) 12:00 pm - (september 16) 1:00 pm Len Hill ParkEvent Type :OtherEvent City:Big Sky

Advertisements

X
X