Arts & Entertainment
MDT bridge decks project progressing smoothly
Published
4 years agoon
Posted By
AdminBy Brandon Walker EBS STAFF
BIG SKY – The Montana Department of Transportation is in the midst of construction on two bridge deck reconstruction projects in Big Sky, with a third slated to begin in July. The projects’ anticipated completion dates vary, but all will be completed before winter snow blankets the ground.
MDT’s contractor, Dick Anderson Construction, began the remodel project at the end of May. Currently, crews are working to revamp bridges that cross the West Fork of the Gallatin River, located near the entrance of the Conoco Travel Shoppe on highway 64, as well as one that traverses the Middle Fork of the Gallatin River, near the Highway 64 intersection with Little Coyote Road.
“The Middle Fork structure, which is the farthest one, they are currently removing Phase 1 of the bridge deck and then once they get that removed, they will start forming up and placing the rebar and all that stuff to pour Phase 1,” said MDT project manager Craig Walker. “Then on the West Fork structure, which is down by the Conoco station, they’ve already hydro milled Phase 1, so they’re prepping to pour back Phase 1 and the pour is scheduled to be on [June 19].”
Walker said that there have been no delays to the $2 million construction project and they are progressing as planned. Each construction area currently allows for one lane of traffic to proceed through the work zone at a time and is monitored remotely by Dick Anderson Construction utilizing cameras mounted on the traffic signals.
“So, they detect the last car and when the last car goes through the light and out the other light, the detection sees that, and the camera sees that and during the high traffic volume times they actually have someone monitoring them to change timing,” Walker said. “If we need to let one direction go longer, they can manually let that direction go longer.”
Walker detailed that the crews assist one another at each site and can only proceed as they receive materials from their suppliers, specifically concrete. “They can only get concrete from their supplier when he’s available to get it to them,” he said.
The West Fork bridge is anticipated to be completed by the end of July, at which point crews will begin construction on a third bridge, located on U.S. highway 191 that is slated to finish in September. “It’ll be the same as the West Fork structure, [the] same process,” Walker said in regard to the work being done on the highway 191 bridge. The Middle Fork bridge will take the longest of the three, needing the most extensive repairs and will finish in November at the latest.
Walker would like to remind travelers to not block the entrances to the Conoco or Chamber of Commerce and at the Middle Fork Bridge, to not detour in an attempt to avoid the project. “That can cause some issues later on if they continue to do it,” he said.
“Go slow through the work zone. It’s, you know, not just for our benefit but for everybody’s benefit. We don’t want anybody not to go home at the end of the day,” Walker said.
Additional MDT area project timelines and overviews
Paving Highway 191 & Adding rumble strips
- July: A few miles at a time crews begin paving the stretch from Tepee Creek Trailhead to US Forest Service Road 986.
- August: Crews will finish paving and place rumble strips along the corridor. All major work will be completed by the end of the month.
Rainbow Point Road turn lane
- June: Construction began at the intersection of Highway 191 and Rainbow Point Road to add a northbound left turn lane. Crews are milling and excavating in the immediate area.
- Late June & early July: Crews pave the area and stripe, or paint, the road. Construction on the turn lane anticipated to finish.
Bridges over Gallatin River & Specimen Creek
- June: Crews finish bridge repairs over Specimen Creek. A concrete surface is laid down on the Gallatin River bridge and takes at least 14 days to cure on each side of the bridge.
- July: Work on the Gallatin River bridge anticipated to be completed.
Upcoming Events
april, 2024
Event Type :
All
All
Arts
Education
Music
Other
Sports
Event Details
Saturday, March 23rd 6:00-8:00pm We will combine the heart-opening powers of cacao with the transcendental powers of breathwork and sound. Together, these practices will give us the opportunity for a deep
more
Event Details
Saturday, March 23rd 6:00-8:00pm
Time
March 23 (Saturday) 6:00 pm - April 23 (Tuesday) 8:00 pm
Location
Santosha Wellness Center
169 Snowy Mountain Circle
Event Details
We all are familiar with using a limited palette, but do you use one? Do you know how to use a
more
Event Details
We all are familiar with using a limited palette, but do you use one? Do you know how to use a limited palette to create different color combinations? Are you tired of carrying around 15-20 different tubes when you paint plein air? Have you ever wanted to create a certain “mood” in a painting but failed? Do you create a lot of mud? Do you struggle to achieve color harmony? All these problems are addressed in John’s workbook in clear and concise language!
Based on the bestselling “Limited Palatte, Unlimited Color” workbook written by John Pototschnik, the workshop is run by Maggie Shane and Annie McCoy, accomplished landscape (acrylic) and plein air (oil) artists,exhibitors at the Big Sky Artists’ Studio & Gallery and members of the Big Sky Artists Collective.
Each student will receive a copy of “Limited Palette, Unlimited Color” to keep and take home to continue your limited palette journey. We will show you how to use the color wheel and mix your own clean mixtures to successfully create a mood for your paintings.
Each day, we will create a different limited palette color chart and paint a version of a simple landscape using John’s directives. You will then be able to go home and paint more schemes using the book for guidance.
Workshop is open to painters (oil or acrylic) of any level although students must have some basic knowledge of the medium he or she uses. Students will be provided the book ($92 value), color wheel, value scale and canvas papers to complete the daily exercises.
Sundays, April 14, 21 and 28, 2024
Noon until 6PM.
$170.
Time
14 (Sunday) 12:00 pm - 28 (Sunday) 6:00 pm
Event Details
Trivia from 7 to 9 p.m. at The Waypoint in Town Center. Participation is free, food and beverages available.
Event Details
Trivia from 7 to 9 p.m. at The Waypoint in Town Center. Participation is free, food and beverages available.
Time
(Wednesday) 7:00 pm - 9:00 pm
Location
The Waypoint
50 Ousel Falls Rd